Facts

The Plaintiffs contracted with the Defendant, a building contractor, to construct a house for $202,000. Due to an error, the house built was significantly larger than agreed upon, leading to financial difficulties for the contractor, who failed to pay material suppliers and subcontractors. After paying $192,000, the Plaintiffs discovered liens exceeding $60,000 filed against the property by suppliers and subcontractors (paras 2-3).

Procedural History

  • District Court of San Juan County: Validated the liens filed by the suppliers and subcontractors, awarded them the amounts of their liens plus attorney fees and costs, and held the Plaintiffs liable for these amounts. The Plaintiffs were awarded judgment against the contractor for the total lien amounts and attorney fees, less certain offsets (para 3).

Parties' Submissions

  • Plaintiffs/Appellants: Argued that the Defendant supplier misapplied payments made by the contractor, which should have been applied to their account. They also contended that the liens should be partially invalidated because they had already made partial payments to the contractor before the liens were filed (paras 3-4).
  • Defendant/Appellee (Houston Lumber): Cross-appealed the award of attorney fees but did not file a memorandum opposing the proposed affirmance of the judgment (para 3).
  • Defendant/Appellee (Farnsworth): Cross-appealed the measure of damages used by the trial judge but did not file a memorandum opposing the proposed affirmance of the judgment (para 3).

Legal Issues

  • Did the Defendant supplier misapply payments made by the contractor, which should have been applied to the Plaintiffs' account?
  • Does the statutory language of "all and any amounts due and owing" allow for partial payments to discharge liens?

Disposition

  • The Court of Appeals affirmed the district court's judgment in all respects, including the validation of the liens and the awards of damages and attorney fees (paras 1, 15).

Reasons

Per Pickard J. (Donnelly and Alarid JJ. concurring):

Misapplication of Payments: The Court found that the Defendant supplier did not know the source of the payments made by the contractor and was therefore free to apply those payments to any accounts as necessary to protect its interests. The Plaintiffs' argument that the supplier violated its own policy was rejected, as the supplier was not bound to apply payments to the Plaintiffs' account without knowledge of the source of funds (paras 4-6).

Statutory Interpretation of "All and Any": The Court held that the statutory language requiring payment of "all and any amounts due and owing" means full payment of the contract price is necessary to discharge liens. The addition of "and any" to the statute was interpreted as emphasizing the requirement for full payment, not allowing partial payments to discharge liens. The Plaintiffs' proposed interpretation was rejected as it would undermine the purpose of the lien statute and render it ineffective (paras 7-14).

Equity Considerations: The Court noted that equitable considerations do not override the statutory requirement for full payment unless the creditor knew the source of the funds, which was not the case here. The supplier's actions were deemed neither unfair nor inequitable (paras 5-6).

Legislative Intent: The Court emphasized that the legislature did not intend to change the existing rule requiring full payment to discharge liens when it amended the statute. The Plaintiffs' arguments for proportional discharge of liens or limiting recovery to the unpaid contract balance were unsupported by the statutory language (paras 9-14).

The Court concluded that the Plaintiffs' partial payments were insufficient to discharge the liens, and the judgment of the district court was affirmed (para 15).