Facts

The Plaintiff, a contractor, entered into a contract with the Defendant for the construction of a small arms firing range. The Defendant provided plans and specifications indicating the removal of approximately 2,400 cubic yards of rock. The Plaintiff relied on this representation in formulating its bid and subcontractor agreements. However, the actual amount of rock removed was significantly higher, leading to additional costs for the Plaintiff (paras 1-2).

Procedural History

  • District Court of Bernalillo County: The trial court granted a directed verdict in favor of the Defendant, concluding that no reasonable jury could find the Defendant negligent based on the evidence presented (paras 1, 23).

Parties' Submissions

  • Plaintiff-Appellant: Argued that the Defendant negligently misrepresented the amount of rock to be removed, causing financial damages. The Plaintiff contended that the plans and specifications were part of the contract and not disclaimed, and that reliance on these representations was reasonable (paras 2, 7-9, 16-17).
  • Defendant-Appellee: Claimed that it had reasonable grounds to believe its representations were accurate, as they were based on an engineering report. The Defendant argued that disclaimers in the soil investigation report and the opportunity for bidders to conduct their own investigations precluded liability (paras 7, 13, 25-27).

Legal Issues

  • Did the trial court err in granting a directed verdict in favor of the Defendant by removing the case from the jury?
  • Was the Defendant negligent in misrepresenting the amount of rock to be removed in the project plans and specifications?
  • Did the Plaintiff reasonably rely on the Defendant's representations?

Disposition

  • The Court of Appeals reversed the directed verdict and remanded the case for a new trial (para 18).

Reasons

Per Chavez J. (Alarid J. concurring):

The Court found that the trial court erred in granting a directed verdict because there was sufficient evidence for a jury to reasonably find in favor of the Plaintiff. The Defendant's plans and specifications, which included a specific estimate of rock removal, were part of the contract and not disclaimed. The Court emphasized that general disclaimers in the soil investigation report did not absolve the Defendant of liability for positive representations made in the contract documents (paras 7-8).

The Court also held that whether the Defendant had reasonable grounds to believe its representations were true and whether the Plaintiff justifiably relied on those representations were questions of fact for the jury. The evidence, including the engineer's recommendation for further testing and the Defendant's decision not to conduct additional tests, could support a finding of negligence (paras 9-10, 16-17).

The Court reiterated that directed verdicts should only be granted when no reasonable jury could find for the non-moving party. Here, the evidence presented conflicts and contradictions that should have been resolved by the jury, not the trial court (paras 11, 16-17).

Donnelly J., dissenting:

Donnelly J. would have affirmed the trial court's directed verdict, arguing that the Plaintiff failed to establish that the Defendant had no reasonable grounds to believe its representations were true. The Defendant relied on an independent engineering firm's report, which included disclaimers and recommendations for further testing. The Plaintiff was aware of these disclaimers and chose not to conduct its own investigation. Donnelly J. concluded that the evidence did not support a finding of negligent misrepresentation and that the trial court properly removed the case from the jury (paras 23-31).