Facts

The case arises from a dispute over a purchase and sale agreement for the construction of a log cabin home. The Plaintiff, a construction company, alleged it completed the construction of the home but was not paid the balance due by the Defendants, a married couple. The Plaintiff filed a complaint to foreclose a mechanic's lien on the property, while the Defendants argued that the dispute should be resolved through arbitration as required by the agreement. The Defendants also claimed the Plaintiff was a shell corporation and sought to arbitrate claims against another individual they believed to be the actual contracting party (paras 4-7).

Procedural History

  • District Court, June 13, 2003: Denied the Plaintiff's motion to stay arbitration and ordered the Plaintiff to participate in arbitration. The court also included ambiguous certification language regarding the appealability of the order (paras 8-10).

Parties' Submissions

  • Plaintiff-Appellant: Argued that it should not be compelled to participate in arbitration and sought a determination of the proper parties to the lawsuit (paras 7-8).
  • Defendants-Appellees: Contended that the Plaintiff was a shell corporation and that arbitration was required under the agreement. They sought to arbitrate claims against another individual they believed to be the actual contracting party (paras 7-8).

Legal Issues

  • Was the district court's June 13, 2003 order a final, appealable order?
  • Did the district court abuse its discretion in certifying the order for appeal under Rule 1-054(B)(1)?
  • Was the Plaintiff's application for interlocutory appeal timely?

Disposition

  • The appeal was dismissed on the grounds that the June 13, 2003 order was not a final, appealable order (para 17).

Reasons

Per Cynthia A. Fry J. (Bustamante and Robinson JJ. concurring):

  • The court determined that the June 13, 2003 order was not final because substantive issues, such as the priority of liens between the Plaintiff and a mortgage company, remained unresolved in the district court. Additionally, the arbitration would need to resolve preliminary matters before the district court could address the remaining issues (paras 11-12).
  • The court found that the Plaintiff's application for interlocutory appeal was untimely, as it was filed 17 days after the district court's order, exceeding the 15-day limit under Rule 12-203(A) NMRA (para 14).
  • The district court abused its discretion in certifying the order under Rule 1-054(B)(1) because the issues referred to arbitration were intertwined with unresolved issues in the district court. Allowing the appeal would risk piecemeal litigation, which is disfavored (paras 15-16).